13.86   Energy Management Control System Acceptance Test Procedure, Use Form NRCA‐MCH‐18‐A

Test Procedure

Construction Inspection

Ensure the following actions have been completed:

•      Factory start-up and check-out complete        

•      I/O point lists available          

•      Point-to-point verification completed                                                  

•      Sequence of operations of each system are programmed                   

•      Written sequences are available                     

•      Input sensors are calibrated               

Verification Checks

Conduct the following verification checks to validate the functionality of the EMCS:

•      Verify the control graphics represent the system configuration

•      Verify control points are properly mapped to the graphics screen

•      Raise and lower a sampling of space temperature setpoints in the software and verify the system responds appropriately

•      Verify the time-of-day start-up and shut-down function initiates a proper system response

•      Verify trending capabilities by establishing trend logs for a sampling of control points

•      Verify alarm conditions are monitored

•      Verify the EMCS panel is installed on an emergency power circuit or has adequate battery back-up